Project Update

Work continues along Meadowhall Road.  Excavation work is now complete and although bases and walls are still under construction in some sections, much of the wall which has already been built is now brick clad and copings are being added. Traffic management will remain in place until the end of October at which point it will be scaled back and Hadfield Bridge will be re-opened to pedestrians.

Work is still being carried out within the Forgemasters site and in the Riley’s Tools area and there are some finishing works to be carried out at a couple of other sites.

Channel maintenance work is still focused on invasive species treatment and a well attended volunteer day took place this week along the river at Effingham Street where volunteers pulled debris from the river and islands.